The design phase is progressing well and is planned for completion by December 2019. This will be followed by the procurement phase and construction starting in early 2020.

  • With regard to landowners’ comments that no approaches have been made for property acquisitions, they are still completing preparatory works before contacting landowners. The design being progressed involves sealing the current road alignment, so any new land requirements will be minimised.
  • At this stage, the first section proposed for construction (referred to as Stage 2) is the section with chainage starting at 5,875m through to 10,075m as measured from West Coast Road.
  • The timing of construction of the Stage 1 section, chainage 850m to 5,875m,will be dependent on budget availability.
  • Communication with the local board and the local community will be undertaken as the project approaches the construction phase and once a contract has been awarded. Prior to works commencing there will be specific communications around the construction methodology, timing etc., all with the aim of minimising disruption.