AT have confirmed the following timetable for sealing Ahuroa Road:

  • Presently under preliminary investigation.
  • March 2019 – Design phase
  • November 2019 to 2021 Construction phase
    Length 8.5 Km (i.e. fully sealed).

Expectation that at $5 million per annum there will be enough budget.

I am still communicating with the powers to be on why they are not allocating more of our money on road sealing. Shane Ellison the CEO of AT has admitted that is has been diverted into higher priority projects like the City Rail Link. AT reduced what seemed like a $12.1 million allocation (the Mayor announced $121 million over 10 years) to $4.7 million this year and $5 million next year. It appears that AT are “uncontrolled” and are to blame for the lack of road sealing progress. Either the Mayor and Auckland Council have lost control of AT or they are both in cohorts misleading the Rodney Rural public.

Unfortunately, unless we do something about it, our side roads will not be sealed within our lifetime, but downtown Auckland will be fabulous! Think about it every time you fill up with gas with the RFT or paying the new Local Target Transport Rate. Us rural people are being screwed by Auckland Council and Auckland Transport.

I will give a more informed update shortly.

Glen
p.s. Only 8.7 Km of new seal since 9 years in Super City.